SCHEDULE & DELIVERABLES ANTICIPATED PROJECT SCHEDULEPROJECT DELIVERABLES AVAILABLE FOR DOWNLOAD Milestone Date Status Notice to Proceed November 19, 2012 Issued Topographic Base Mapping December 24, 2012 Completed Rueter-Hess Adequate Assurances Agreement November 13, 2014 Completed Draft Baseline Hydrology January 2015 Completed Final Baseline Hydrology March 2015 Completed Draft Alternatives Analysis April 2015 Completed Draft Flood Hazard Area Delineation May 2015 Completed Final Alternatives Analysis May 2015 Completed Revised Draft Flood Hazard Area Delineation September 2015 Completed Draft Conceptual Design Report September 2015 Completed Final Conceptual Design Report October 2015 Completed Final Flood Hazard Area Delineation November 2015
SCHEDULE & DELIVERABLES
ANTICIPATED PROJECT SCHEDULE
PROJECT DELIVERABLES AVAILABLE FOR DOWNLOAD