udfcd.jpg (6087 bytes)

FLOOD HAZARD NEWS
Vol. 25, No. 1 December, 1995

The Lower Central South Platte River Through Denver
by: Leo M. Eisel, Ph.D., P.E., President and Brian S. Kolstad, P.E., Project Manager, McLaughlin Water Engineers, Ltd.

Introduction

The 10.5 mile reach of the South Platte River through Denver extends from the south City limits near the Bi-City Treatment Plant to the Burlington Ditch near the north City boundary. Included in this reach are:
19 parks adjacent to the river.
More than 12 miles of recreational trail immediately adjacent to the river and connecting to another 6 trails with an additional 50 miles of trails.
A wastewater treatment plant and a decommissioned wastewater treatment plant.
Two power plants.
10.5 miles of riparian habitat.
10.5 miles of river habitat transitioning from the cold water habitat of the foothills to the warm water habitat of a prairie river.

Surrounding this reach is a metropolitan area with more than 2 million people who demand numerous goods and services dependent on the South Platte River and its corridor including:
Flood hazard mitigation
Municipal and industrial water supply
Recreation
Wildlife habitat

Multiple-Purpose Planning Required

In order to meet these goals and successfully carry out the numerous action items, the Urban Drainage and Flood Control District cooperated with the City and County of Denver to conduct multiple-purpose water resource planning. Providing flood hazard mitigation and reclaiming Denver's Central South Platte River requires responding to the many needs and demands while insuring that existing stakeholders including communities, industries, a power company, recreational users, fish and wildlife agencies, environmental regulatory agencies and existing residents are kept whole in the process.

At the same time, constraints and limitations exist that restrict the reclaiming process including limited funding, conflicts among goals, institutional conflicts, and a finite South Platte River water supply. To facilitate this process, multiple-purpose water resources planning has been employed by Denver and the District in order to produce a series of feasible projects, programs and policies acceptable to the many stakeholders and for which necessary funding can be obtained for construction and implementation.

Project Implementation

The recently completed $7.5 million project at Confluence Park demonstrates a successful flood hazard mitigation project which also provides important opportunities for boating and recreational access to the river together with the addition of 5 acres of wetlands, reconstruction of a 24 cfs diversion structure for year around power plant cooling water, and wildlife and aquatic habitat.

The on-going Upper Central South Platte Valley at Zuni design project expands the purposes further to include expansion and improvement to the riparian and wildlife habitat, recovery of the South Platte fishery in the reach, providing recreational access to the river, provision of a safe boating drop structure, and diversion of cooling water for another power plant, along with meeting all flood control objectives.

These projects demonstrate that urban flood hazard mitigation projects can produce significant benefits for a wide range of urban stakeholders and downstream reaches as well.

Confluence Park to I-25 Project

The multiple-purpose project in this reach consists of:
Removing the old diversion dam, intake and boat chute.
Constructing a new diversion dam with a crest approximately 3 feet lower which is also expected to improve aquatic habitat downstream.
Constructing a new and more efficient power plant cooling water diversion structure.
Widening the boat chute and improving the drops for an improved boating experience and adding fish passage.

The accompanying photographs present two views of the Confluence Park diversion dam, boat and fish passage chute, trail and plaza complex. Due to the complex hydraulics, a physical model study was completed to determine hydraulics through the area while providing a starting water surface for the analysis of the flood profile for an enlarged channel between Speer Boulevard and I-25 adjacent to the new Elitch Gardens amusement park. Other additions included widening of an existing pedestrian bridge, new ADA approved ramps on both sides, an east side plaza and access to the river, connections to the new trail/maintenance road and landscaping using primarily native species. The channel in the reach upstream of Speer Boulevard to I-25 was lowered an average of 3 feet and the east bank widened approximately 100 feet. The toes of the slopes were lined with riprap to prevent the typical scour and bank sloughing previously experienced.

Two Views of Confluence Park

Left:  Looking directly upstream, the existing plaza is in the lower right with the new diversion dam center right and the new boat chute and plaza center left.
Right:  Looking down on the park the new diversion dam is on the lower right, the new boat chute and plaza goes from lower left to upper right, and the widened pedestrian bridge is across the top of the picture.

A maintenance road/trail was added to the east bank and landscaping was added using different zones. The area at the water edge was planted with 10,000 live staked willows and the riparian zone immediately up the bank with a water table located approximately 2 feet below the surface was planted with wetland-type plants such as arctic willows. The steeper slopes of the east bank were planted with a variety of native trees and shrubs including choke cherry and rabbit brush. Approximately 300 trees and over 3,500 shrubs were planted along the east bank and Confluence Park.

Trees included primarily native species hackberry, hawthorn, juniper, cottonwood and choke cherry. Shrubs included rabbitbrush, dogwood, juniper, western sandcherry, coyote willow and dwarf arctic willow. The Colorado Division of Wildlife's list of trees and plants was used to select plantings.

The 1995 spring storms affected the project by depositing silt behind the dam and creating sandbars in the channel. Due to the wet spring and late snows during 1995, the South Platte River sustained flow for April, May and June varied between 2,000 and 4,000 cfs; the more typical monthly flow for the Platte in this reach is approximately 200 cfs. Four hydrograph peaks near the 10-year flow event (approximately 9,000 cfs) occurred in the April to June period. These 1995 spring flows provided a good test of the structural integrity of this multiple-purpose project.

South Platte River Zuni Reach Project

The Zuni reach has a diversion dam just downstream of Thirteenth Avenue to provide cooling water for the Public Service Company's Zuni Power Plant. The existing diversion depends on a rubberized inflatable dam. The dam height fluctuates depending upon the amount of flow in the river. There is presently no boat chute for this obstruction and boaters must now portage around the dam. Due to constrictions of the Thirteenth and Fourteenth Avenue bridges and low banks upstream, there is widespread flooding in this reach. The current plan is to increase flood conveyance capacity of the channel by reshaping the channel from I-25 to Eighth Avenue and eliminating the existing inflatable dam. Implementation will include improvements to the river's fish habitat, boating, landscape, aesthetics and wildlife habitat.

Conclusions

Implementation of the Confluence Park to I-25 reach and the design process for the Zuni reach of the South Platte River through the Central Denver flood hazard mitigation project indicates the absolute necessity for multiple-purpose flood hazard mitigation projects in urban areas. Without designing and constructing these projects to incorporate numerous features for a wide variety of stakeholders, successful design, funding, and construction of these projects would not be possible.

1995 Professional Activities of District Staff

Scott Tucker, Executive Director

*Chaired program on Stormwater Management at National Association of Flood and Stormwater Management Agencies (NAFSMA) annual conference, in Washington, D.C. in November.

*Member of Board of Directors and Chairman of the Stormwater Management Committee of NAFSMA.

*Menber of the Stormwater Phase II Advisory Subcommittee, formed pursuant to the Federal Advisory Committee Act to assist in developing the Phase II stormwater program.

*Chairman, History and Heritage Committee, Colorado Section, American Society of Civil Engineers.

*Guest lecturer at Environmental Science Class, Metro State College in Denver.

*Chapter Delegate for Colorado Chapter of American Public Works Association.

Bill DeGroot, Chief, Floodplain Management Program

*Elevated to Fellow of the American Society of Civil Engineers.

*Appointed Chair of the FEMA Liaison Committee of the National Association of Flood and Stormwater Management Agencies (NAFSMA), and chaired a panel discussion on FEMA Issues at NAFSMA's annual meetine in Washington, D.C. in Nov.

*Panelist at the 20th Annual Hazards Research and Applications Workshop in Boulder, Colorado in July.

*Secretary of the Colorado Natural Hazards Mitigation Foundation.

*Member of the Colorado Natural Hazards Mitigation Council.

Kevin Stewart, Project Engineer, Floodplain Management Program

*National Hydrologic Warning Council (NHWC) Representative for the Southwestern Association of ALERT Systems (SAAS).

*Member of the Colorado Natural Hazards Mitigation Council's Dam Safety and Warning Subcommittee.

*Speaker at ALERT Users Group annual conference in Pacific Grove, California in May and at the SAAS conference in Tulsa, Oklahoma in October.

*Represented the NHWC at the National Weather Service/FEMA Emergency Management Forum in Arlington, Virginia in March and presided at the First National Conference of the NHWC in Baltimore, Maryland in June.

*Panel discussant on "Local Emergency Management Critical Information Requirements" at the 20th Annual Hazards Research and Applications Workshop in Boulder, Colorado in July.

*Speaker on "US Approach to Flood Warnings and District's Approach to Local Flood Warnings" at the Current Issues in Total Flood Warning System Design Workshop, Flood Hazard Research Centre, Middlesex University, London, England in Sep.

Ben Urbonas, Chief, Master Planning & South Platte River Programs

*Organized and chaired a session on the topic of BMP Effectiveness at the ASCE Water Resources Planning and Management Division's Specialty Conference in Boston in May.

*Continues to Chair the Urban Gauging Networks Committee of the Urban Water Resources Research Council of ASCE.

*Re-elected in September to the National Board of Directors of APWA's Institute for Water Resources.

*Continued to serve as a member of the Control Group of the Urban Water Resources Research Council of ASCE.

*Moderated an APWA-IWR sponsored professional development session on Watershed Planning and GIS at the APWA Exposition and Congress in Dallas in September.

*Co-chair of the Water Environment Federation effort to publish a Stormwater Quality Management Manual of Practice. Publication is expected next summer.

*Had a paper published in the ASCE Journal of Water Resources and Planning and Management, titled "Recommended Parameters to Report With BMP Monitoring Data," February, 1995.

*Was notified by ASCE Journal of Water Resources and Planning and Management of the acceptance of a paper co-authored with Dr. C.Y. Guo titled "Maximized Detention Volume Determined by Runoff Capture Ratio" for publication in February, 1996.

*Had a paper titled "Hydrology for the Management of Stormwater Quality," accepted for publication in the Water Quality International Journal. Co-authors are Larry A. Roesner, Ph.D. and James C.Y. Guo, Ph.D.

John Doerfer, Project Hydrologist, Master Planning Program

*Chairman of the Stormwater Quality Committee, Colorado Association of Stormwater and Floodplain Managers (CASFM).

*"Inventory of Structural BMPs in Urban Areas of Colorado," presented at 1995 CASFM conference in Colorado Springs in Nov.

*Guest Speaker at CASFM workshop, "Construction Erosion BMPs - A Management Perspective." in Greeley in Nov.

Mark Hunter, Chief, Maintenance Program

*Member of International Erosion Control Association (IECA) standards committee on riprap, standards committee on articulating blocks, and the by-laws committee.

*Secretary of the Steering Committee for the IECA-Mountain States Chapter.

*Panel member for the review and evaluation of proposed testing protocol for articulated concrete block, a Colorado State University project for the U.S. Army Corps of Engineers.

Paul Hindman, Project Engineer, Design and Construction Program

*Vice-Chairman of the Institute of Water Resources of the Colorado Chapter of APWA.

*Treasurer of the Colorado Chapter of APWA.

Tucker-Talk
by
L. Scott Tucker
Timely Comment from the District's Executive Director

The Urban Drainage and Flood Control District was established in 1969 by the Colorado State Legislature and in 1994 the organization celebrated its 25th year of service in the Denver metropolitan area. In the 1994 issue of Flood Hazard News I talked about the first 25 years of the Urban Drainage and Flood Control District and touched on where things might be headed in the future.

Times have certainly changed since 1969. In the early days flood control was the primary problem and typically was considered a single-purpose issue. The Urban Drainage and Flood Control District, however, since the beginning has had the vision of using drainageways as open green corridors to the maximum extent possible. Most of our projects have public access and multiple uses of the drainage corridors are encouraged. A big change since 1969 is the increased emphasis on, and interest in environmentally sensitive issues and the view of flood control as only one part of a multiple-use, multiple-faceted problem, or in some cases, opportunity. The increasing environmental sensitivity of the public will likely continue and one result will be a shift in interest to "naturalization" of urban stream corridors wherever possible. There will be a tendency to de-emphasize structural projects, and stabilization of natural streams will become an even more important activity as time goes on.

The public also has an interest in improving the quality of our water systems including small streams and gulches, rivers, lakes, estuaries, and oceans. Since 1972, when the Federal Water Pollution Control Act was first passed, the focus has been on addressing point sources of pollution from both municipal treatment facilities and industrial facilities. This has been a heavily federally subsidized program with early efforts being funded by as much as 90% by the federal government. Recently this has changed to a revolving fund concept and there is more funding at the local level. This effort has been successful in reducing pollution from point sources and the improvement in our receiving waters has been significant.

However, as the "point" sources are being controlled, more attention is shifting to the "non-point" sources of pollution. Non-point sources of pollution are generally a wet weather phenomenon and come from many sources including agriculture, silvaculture, the air, mining, urban areas, etc., and are much more difficult to address. It was relatively easy to identify where the sewage needed to be treated and, when 75 to 90% of the funding was provided by the state and federal governments, there was a limited financial impact on local governmental entities. Non-point source pollution on the other hand is much more difficult to identify in terms of where it is coming from and the impact it is having on receiving waters. It is also much more difficult to control because it comes from many small sources such as individual farms, homes, industries, commercial establishments, highways, mines, etc., etc.

Runoff in urban areas is one of the non-point sources of pollution that is being looked at closely. According to present law and regulations, storm sewer discharges in cities over 100,000 population and from most large industrial sites, defined as Phase 1 stormwater sources, are considered to be point sources of pollution. As such these cities and industries have been required to submit applications for NPDES (National Pollution Discharge Elimination System) permits. Many cities have been issued NPDES permits for their stormwater systems and others are still waiting for permits to be issued. The parameters of the permit program are defined by EPA and administered in most states by the state permitting agency; and by EPA in about ten states that are non-delegated states. It is a command and control system and local governments are being forced to react to the federal mandate. This has created an adversarial relationship and has inhibited the development of federal, state and local partnerships.

Also at this time, EPA is considering how to address the remaining municipal and industrial and commercial stormwater discharges. These stormwater discharges have been defined as Phase 2 discharges. Pursuant to the Federal Advisory Committee Act (FACA) EPA has established a committee to advise them on how to address the Phase 2 discharges. The Phase 2 FACA committee is comprised of approximately 35 individuals representing many different interest groups including industry, environmental, state, federal, Indian tribes and local governments. The charge to the committee is to reach a consensus recommendation regarding how EPA should address the task of reducing pollutants in Phase 2 stormwater discharges.

The problem with the approach to addressing Phase 1 and Phase 2 sources of stormwater pollution, in my view, is that it has not been approached as a federal-state-local partnership. The direction has been defined at the federal level and local governments have been required to seek permits under the threat of fines and penalties. This has created an adversarial relationship and has inhibited the development of real partnerships in addressing stormwater quality issues.

It cannot be denied that urbanization has significant impacts on the environment. What was once a natural prairie with tall grasses, trees, running streams and so on totally changes character when it becomes an urban area with buildings, streets, people, houses, cars, etc. Since the industrial revolution society has been moving from rural areas to urban centers. This is a movement that is beyond our control and must be recognized and dealt with realistically. People are free to move about. There is no effective way to prohibit people from moving into a metropolitan area. Therefore, urbanization is likely to continue.

However, this is not to say that we must forsake or abandon our environmental interest and concerns. While it may be unrealistic to preserve a stream or river in a pre-development condition, we can manage and protect our water resources to be high quality assets for our urban areas. The public is interested in the water resource and highly values lakes and streams of a quality that does not prohibit their use of them. The public is also interested in creating and preserving wetlands, controlling erosion, and in reducing the pollutants that enter their receiving waters. I must also add that the public is still very interested in flood protection. When lives are lost and property is damaged due to flooding, that problem becomes the number one priority. Fortunately good flood management and water quality management are not mutually exclusive.

Since the water pollution control act was passed in 1972 the basic approach has been through a command and control permitting system. This permitting system was designed and intended for point sources of pollution from sources such as municipal treatment plants and industrial treatment facilities. As the emphasis in the nation shifts from the classic point sources to non-point sources, and I include municipal stormwater as a non-point source, we are finding that the classic NPDES command and control permit system does not work so well. EPA has tried to make the NPDES system work for large cites over 100,000, but they are facing a difficult task because the permitting system was not designed to be applied to such diffuse sources of discharge. EPA and the states are now faced with demanding permits of general purpose governments and dictating to them how they should manage their stormwater systems. This has created an us-versus-them mentality and has inhibited the development of productive federal­state­local partnerships. Since we are all representing the same constituency, the people, logic would dictate or indicate that we turn away from the top down command and control approach now employed to one of true partnership and cooperation.

Now might be the time we start thinking about a different approach to non-point sources of pollution, a new paradigm if you will. I think all would agree that the municipal stormwater program will be implemented by local governments. That is where the buck stops. Local governments exist because people live in urban areas and certain basic functions need to be provided, such as police, fire protection, libraries, roads and streets, parks, and good water quality. Local governments and their citizens want and need these basic services, and they are the ones that pay for them. Now is the time for local governments to step forward and take the initiative to develop good stormwater management practices that will presumably lead to improved water quality. Federal and state agencies need to work with local governments in defining what water quality problems are caused by urban stormwater runoff and what steps can be taken to mitigate those problems. Local governments need to be a part of the problem definition if they are expected to bear the primary burden in solving the water quality problems. While we can't change the fact that urbanization will dramatically change the environment which includes streams, creeks and lakes, we can manage that change so that the receiving waters that are impacted by urbanization maintain an intrinsic value to the community that is founded on good water quality. This means that local governments must practice good erosion control, good housekeeping, must educate their citizens as to the value of their natural resources, and must maintain their water resource facilities.

There is also the matter of finite resources. Local governments only have a certain amount of money to deal with. They cannot solve every problem. Stormwater control might be a number four concern in one community and a number 20 concern in another community. Communities must be given the flexibility to address those problems they consider to be the most important.

In conclusion I hope that a new partnership consisting of local, state and federal levels of government can be formed to work together to address water quality problems. This partnership must be based on all the partners being at the table on an equal basis, and being included in the process from the very beginning.

District Wins Accounting Award Again

For the seventh year in a row the District has received a "Certificate of Achievement for Excellence in Financial Reporting" from the Government Finance Officers Association of the United States and Canada. The certificate is presented to government units whose comprehensive annual financial reports achieve the highest standards in government accounting and financial reporting. Congratulations to Frank Dobbins, Chief of Finance and Accounting, for continuing this string of awards.

South Platte River Program Notes

by Bryan W. Kohlenberg, P.E., Project Engineer and Ben Urbonas, P.E., Chief South Platte River Program

Maintenance Activities

In 1995 the South Platte River routine maintenance work included an equivalent of 47 miles of trail edge mowing, tree trimming and pruning along 7 miles of the river, and 122 miles of trash and debris pickup and removal. Over 35 truckloads of trash and debris were removed and taken to a landfill. These quantities do not include the trash picked up by the local government personnel nor the trash removed from trash receptacles maintained by park personnel along recreational trails. Although this type of routine maintenance often is not noticed or recognized by the public, without it the South Platte River corridor would have an entirely different "look." It is this type of maintenance that provides the public with a more pleasant experience whenever visiting the many trail and pocket park facilities that now exist along the 41 miles of this river between Chatfield Reservoir and the Weld/Adams County line.

The restoration maintenance program continued to provide repair of erosion damage along the maintenance trail; repairs to the trail and to maintenance access bridges; cutting and removal of a large number of dead elm trees along 10.5 miles of river bank (victims of the Dutch Elm Disease epidemic in 1992­93), restoration of a water diversion/grade control structure at Public Service Company's (PSCo) Arapahoe Plant; and stabilization, restoration, and revegetation of approximately 1800 feet of river bank in Denver (see the article on Chevron gas station site restoration). We expect more bank repair will be needed in 1996 because of extensive bank erosion damage caused last May through August by unusually protracted high flows.

Three large restorative maintenance projects were completed this year. The restoration and stabilization of the west bank of the South Platte River through Denver's proposed Rockmont Park involved bank cleanup, riprap stabilization, revegetation and strategic placement of large boulders, the last being for wildlife habitat improvements and refuge for fish during high flows. The project also included the addition of a low lying wetland planting bench for future planting by the Denver Parks Department during its Phase I of the Rockmont Park development project scheduled for 1996.

The second project was the rehabilitation of the Public Service Company's water diversion structure at the Arapahoe Power Generating Plant. The addition of a boat chute to the structure reduced the unboatable structure count on the South Platte River in Denver to one (PSCo Zuni Power Plant Dam). The chute also doubles as access for fish passage. See the two photographs that show the before-and-after views of this structure. We want to thank the Public Service Company for sharing in the cost of constructing this boat/fish passage chute and for their help during its construction.

araphob.jpg (15445 bytes) araphoa.jpg (15063 bytes)

Before and after views of the PSCo Arapahoe power plant diversion structure.

The third project cleaned up and restored 1200 feet of badly abused river bank in the City of Brighton. The river bank was undermined and collapsing even though part of it was stabilized in the past by the property owner with concrete and asphalt slabs. The overbank was a dump of used construction materials. Brighton purchased this parcel and the District restored and revegetated the bank and overbank. After the restoration was completed, Brighton constructed a 10 foot wide combination recreation and maintenance trail along this bank and planted a large number of trees and shrubs. What used to be a trashed-out area now is a clean open space site that will mature over the coming years into another piece of restored riparian habitat along the river.

Cooperative Projects With Private Property Owners

In exchange for flowage and maintenance access easements the District is now participating in the construction of two cooperative maintenance projects. Both involve much­needed river bank cleanup, stabilization and revegetation. One is the restoration of a degraded river bank owned by Mr. Stanley Miles in Adams County. The other is located at Cooley Gravel Company's North Dahlia Pit north of 88th Ave. in Commerce City.

In 1985 the Miles family received notification in the form of an Administrative Order from the U.S. Environmental Protection Agency (EPA) requiring them to remove unauthorized fill material consisting of refuse, wood, concrete rubble, broken asphalt and other materials, from the river bank adjacent to their property. Faced with the threat of fines of up to $25,000 per day Mr. Miles, on the advice of the EPA, contacted the District to request assistance. In exchange for a permanent flowage and maintenance access easement the District is presently removing and disposing the unauthorized fill, restoring the river bank, stabilizing it with buried riprap and revegetating the restored bank with native grasses and willows. This project poses a challenging problem in that the existing unauthorized fill material to be disposed of provides effective bank erosion protection for the Miles' family home. Also the Administrative Order requires EPA inspection of all material to be removed. Therefore, this project requires creative construction phasing and water control to minimize risk of potential property damage due to construction in a dynamic river channel and close coordination with the EPA during material removal.

The cooperative project with Cooley will restore and stabilize several hundred feet of river bank. We will also construct one river bottom degradation check structure using three to four foot diameter boulders. Cooley Gravel is providing the construction labor and equipment while the District is paying for the materials. We expect this project to be completed by the end of March, 1996.

Readers of past issues of Flood Hazard News may remember the Carlson bank stabilization project completed over two years ago. The accompanying photographs show before and after views of the project. The vegetation effort has been successful - quite a dramatic improvement over the pre-construction situation. We expect even more naturalization in the future.

Before After

Carlson property before and after.

Capital Improvement Activities

During the last year the District has been cooperating with the City and County of Denver to develop and design two major river improvements projects. One is the extension upstream of the Lower Central Platte Valley Project described in the opening article of this newsletter. The design consultant has been working with the project sponsors and the PSCo to develop a way to remove PSCo's inflatable diversion dam at the Zuni Power Plant, while providing the cooling water the power plant needs to generate electricity. Three concepts were proposed and are now being evaluated by PSCo. The concept that Denver likes and which seems to offer the most river improvement potential is to convert the cooling system to a closed loop recirculating system requiring only makeup water for evaporation. Unfortunately it is also the most expensive alternative. A decision on this issue is expected early in 1996. Once made, we will authorize the consultant to complete the design for this 1200 foot reach of the river. We also hope to expand the design to the remaining 4000 feet of this reach in 1996 and begin funding construction in 1997 or 1998. Once constructed, this project will remove approximately 300 acres of central Denver from the 100-year floodplain.

The other capital project is in north Denver's Globeville neighborhood. It involves river improvements and flood control along 7000 feet of the river. Once constructed, it will also remove approximately 300 acres of densely urbanized area from the 100-year floodplain. During the last year the project consultant, Love & Associates, Inc., has prepared the final design for a 2000 foot sub-reach of this project and has also completed a detailed preliminary design for the entire 7000 foot project area. The first phase is expected to go to construction in 1996. In addition to flood control this project includes terrestrial and aquatic habitat improvements, installation of 2000 feet of paved trail and 800 feet of narrow unpaved trails, and many aesthetic and environmental enhancements. The project is located in one of the most densely industrialized areas of Denver where finding room within a confined right-of-way for these types of enhancements is a challenge. Nevertheless, with the input of local citizens and a large number of interested individuals and agencies, a plan emerged. We are very excited to see it begin taking shape in 1996.

Other News

As mentioned above, the Denver Parks Department requested District assistance with the removal of dead trees along the South Platte River. This effort has been on-going since August. At last count, over 1,000 dead trees have been cut down and chipped for use as mulch. The removal of most dead trees within the 10.5 mile reach in Denver should be completed by the end of January, after which the work will extend into Adams County to at least the Sand Creek confluence. Anyone need wood chips?

Last year the City of Littleton, South Suburban Parks and Recreation District, and the Ken Caryl Water and Sanitation District requested the District to buttress a large exposed sanitary sewer crossing just downstream of C-470. The river bottom downstream of the exposed utility crossing has degraded up to ten feet since the crossing was constructed several years ago. The design is now complete and we hope to begin construction in January, 1996. The District and Littleton are funding a rock buttress that will incorporate a fish and boat passage chute.

With District assistance the Denver Parks Department hopes to replace at least two of the remaining six timber pedestrian and maintenance access bridges crossing the South Platte River. These bridges have deteriorated badly over the last 15 to 20 years and have become a constant maintenance problem. They have apparently exceeded their expected design life. This year the District, in cooperation with Denver, retrofitted two badly worn bridge decks with recycled rubber mats commonly used on horse stall floors. This relatively low-cost fix seems to have pleased trail users and, hopefully, extended the deck life for a few more years. This, however, is a temporary reprieve and we hope to see bridge replacement begin soon.

PLANNING PROGRAM ACTIVITIES

by Ben Urbonas Chief, Master Planning Program

STATUS OF PLANNING PROJECTS

Project Sponsor(s) Consultant Status
Upper Box Elder Creek Aurora, Arapahoe Co., Adams Co. CH2MHill Completed in 1995
Columbine Basin Arvada & Wheat Ridge Muller Engr. Corp. Completed in 1995
Dry Gulch Update Lakewood Muller Engr. Corp. Completed in 1995
Stapleton Drainage Denver McLaughlin Water Engr. Completed in 1995
Weaver Creek Tributary Jefferson Co. J. F. Sato Completed in 1995
Westerly Creek U. S. of Havana Aurora Merrick 90% Complete
Niver, Brantner & Grange Hall Cr. Updates Thornton & Adams Co. Kiowa 50% Complete
Arapahoe & Magpie Gulches Golden & Jefferson Co. WRC Engineering 50% Complete
Big Dry Cr. (ARAPCO) Update Arapahoe Co., Douglas Co., Greenwood Village, Englewood, Littleton WRC Engineering 50% Complete
Willow/Little Willow Cr. Douglas Co. n/a Scheduled for 1996
Brighton Basin Brighton & Adams Co. n/a Scheduled for 1996
Cherry Creek - Reservoir to Coungy Line Arapahoe Co. & Cherry Cr. Water Quality Authority n/a Scheduled for 1996
East Henry's Lake Trib. to Bear Creek Denver, Lakewood & Jefferson Co. n/a Scheduled for 1996
City of Englewood OSP Englewood n/a Scheduled for 1996
Pleasantview Area OSP Jefferson Co. & Lakewood n/a Scheduled for 1996
Lower Box Elder Cr. OSP Adams Co. n/a Scheduled for 1997


Planning Projects

The table titled "Status Of Planning Projects" lists the projects that were under way or completed in 1995 and the ones we hope to begin in 1996 and 1997. We will begin the consultant selection process for the 1996 projects as soon as the funding agreements are executed between the District and each project's local sponsors. This could be anywhere from the first two months of the year to late fall.

A total of five projects were completed during 1995. One of these, Outfall System Planning - Dry Gulch (Muller Engineering) replaced a master plan originally published in 1979. The original plan, although optimized for benefit/cost ratio, proved to be unaffordable and was never implemented. The new plan provides for a lesser level of flood protection, but once implemented, will eliminate a very large number of frequently occurring drainage and flooding problems in Lakewood. Affordability is something we now pay attention to when developing new plans. It is often the primary reason why some plans are never fully implemented, since local tax or other revenue often needs to be used to fund them, which revenue is not readily available and needs to compete with other municipal needs.

The Upper Box Elder Creek Outfall System Plan (CH2MHill) was completed in December and covers a 75 square mile portion of a large watershed that has its headwaters in Elbert County. This report covers the largest single area for which we have developed a plan on how to deal with stormwater quantity and quality as the watershed urbanizes.

Box Elder Creek is an ephemeral stream traversing Arapahoe and Adams Counties and City of Aurora. Outside of the small Town of Edwards in the upstream Elbert County, the entire watershed is rural in nature, with some farming and much ranching land use. The three local governments that co-sponsored this plan are concerned about what will happen to the Creek and its many tributaries as urbanization begins to occur.

From experience we know that the tributaries will experience in-stream erosion and will become unstable. Box Elder Creek itself will experience similar effects in its steeper upper reaches and stream aggradation and possible avulsion in the flatter lower reaches, all because surface runoff volumes and peaks will increase with urbanization. The plan has specific recommendations for dealing with these problems, including preservation of greenbelt corridors, and a set of facilities and a general strategy for mitigating stormwater runoff quality from new urban areas.

The Stormwater Outfall System Plan, Stapleton Area (McLaughlin Water Engineers, Ltd.) was co-sponsored by the City and County of Denver through its Stapleton 2000 Office. When the decision was made to close Stapleton Airport, Denver decided to develop a plan for the redevelopment of this seven square-mile site. The City contracted independently with the Stapleton Redevelopment Foundation to come up with the overall redevelopment plan. The District was asked to help the City to develop a stormwater management plan for the redeveloped site. Since over one half of the site did not have a creek, gulch or any other form of readily available receiving system for the increased stormwater volumes and rates, the challenge was great.

The final plan had to address not only difficult technical issues, but also had to address challenging institutional issues. In addition to the sponsors and their consultants, input was sought from a large number of local, state and federal agencies. Since the overall redevelopment plan was being done by Stapleton Redevelopment Foundation, the two had to mesh, or otherwise neither system would work. As it turned out, the major drainage outfall plan played a key role in how the overall plan was laid out. We were fortunate that drainage was recognized as a key element in the Foundation's plan and that the two efforts worked together well to make both plans work as a unit.

The final outfall system plan recommends creating new streams, detention areas, wetlands, and water quality enhancement basins. It also recommends the restoration of Westerly Creek and Sand Creek. Westerly Creek was piped 40 to 50 years ago to build new runways, while Sand Creek was narrowed down by overbank filling. Although we cannot restore these waterways to what they were before urbanization occurred, it is possible to enhance their wildlife and aquatic life character and, once restored, leave two natural greenbelts and riparian corridors for future generations to appreciate and enjoy.

The other two Outfall System Planning projects, namely, Columbine Basin (Muller Engineering) and Bergen Reservoir Tributary to Weaver Creek (J.F. Sato and Associates, Inc.) were much smaller in scale. However they were very important to their sponsors: the cities of Wheat Ridge and Arvada; and Jefferson County. Both planning efforts came up with plans to solve some of the existing drainage problems and how to deal with new urbanizing areas that will affect already existing commercial and residential neighborhoods. Both include recommendations that should help with stormwater quality as well. It will now be up to the local sponsors to take the initiative to implement these plans. The District will help and assist as needed.

Technology Transfer & Education

In our last issue I mentioned that the Colorado Department of Transportation now requires a specialist who has received a Certified Erosion Control Training card to be present on all of CDOT's construction projects, and that Red Rocks Community College is offering this certification (contact Scott Olson at Red Rocks for information: telephone 988-6160, X-282). CDOT has also released its own erosion control manual titled Erosion Control and Stormwater Quality Guide (price $15.00) and a plastic laminated Erosion and Sediment Control Pocketbook (price $10.00). Both are excellent documents and I encourage everyone to obtain them. Contact Philipp Sieber, Colorado Department of Transportation, Specifications Unit, 4201 E. Arkansas Avenue, Denver, CO 80222, Tel. 303-757-9343 to order them.

Software

In the last issue I reported that Curtis Neufeld, a student intern working at the District at that time, has modified the CUHPE/PC code to include a method that accounts for rainfall losses when a watershed has a reduced level of directly connected impervious area (CUHPF/PC). We asked several users of CUHPE/PC to test it and discovered some unforeseen problems, which we think now have been corrected by Curt. We are now again testing the software and once it checks out, it will be released as an update through Computer Software Library, Inc. P.O. Box 27517, Denver, CO, 80227, Tel. 303-947-3413, FAX 303-985-8882, the District's software distribution agent.

Stormwater NPDES Activities

Again very little new to report on this topic. The Clean Water Act is stalled in Congress and no one can predict when it will move forward and how the Clinton Administration and Congress will finally resolve their differences.

The three largest cities in the Denver area submitted their Part 2 Permit Application to the State of Colorado in November of 1992. Since then two draft permits have been released by the State for public comment, but none of the stormwater permits have been issued as of December 1995. The three year effort to issue these permits illustrates the complexity of municipal stormwater discharge permits. The permit issuing effort does not even begin to illustrate the complexities and confusion that will probably arise after these permits are issued and have to be implemented by the municipalities, under the watchful eye of the State. Their very nature affects how, by who, and when specific urban activities will be performed. Keep in mind that the activities required by the permits will take precedence over others in these cities to not be in violation of the permit conditions.

In 1995 Arapahoe County was notified by the State that it now has an urban area population of over 100,000 and this put them into the Phase 1 category for municipal stormwater NPDES permitting. The District is assisting the County as it begins to prepare Part 1 of its application. If we think that the other three applicants had complicated institutional issues, we have seen nothing yet. The County has to address a number of metropolitan, water and sanitation and other special districts that have stormwater responsibilities. In addition, part of the County is also within the Cherry Creek Basin Water Quality Authority. Who will ultimately be responsible for each entity's performance will require agreements between all concerned.

In addition to Arapahoe County, the District continues to assist other cities and counties within its boundaries as they take steps in anticipation of being required to prepare their applications. Should your city or county decide to begin any work toward this goal, or want to develop stormwater system inventories, call us. We can provide you with protocols and data management tools that will help you with the permit applications in the future should your community be required to prepare them.

Stormwater quality and quantity management by municipalities is the right thing to do (see Tucker Talk). Although we do not agree with the "command and control" nature of the Federal mandates and the need for NPDES municipal stormwater permits, we believe that municipalities need to become proactive in dealing with the effects of urbanization on stormwater runoff and the streams in the Denver metropolitan area.

It cannot be denied that stormwater runoff from urbanized areas has an effect on the receiving waters. Many of these effects can be greatly mitigated through the use of best management practices (BMPs). Where we have newly urbanizing areas the use of structural BMPs can significantly reduce the intensity of runoff and improve its water quality, especially from the most frequently occurring smaller rainstorms. The use of non-structural BMPs in these areas can further improve the quality of runoff and can definitely help to improve the water quality of surface runoff from already urbanized areas.

We will continue to work at lessening Federal mandates and their command and control nature on how municipalities do their business in managing stormwater. However, we also need to become advocates of doing the right thing, whatever that may be. To help with this task we published, after considerable coordination with a number of municipalities, the state, and others in this region, Volume 3 - Best Management Practices of the Urban Storm Drainage Criteria Manual.

This manual provides, what I believe to be, reasonable and cost effective techniques on how to design structural BMPs, how to use non-structural BMPs, and how to deal with erosion and sedimentation from construction sites. We urge you again to familiarize yourselves with this publication and see if you can incorporate its techniques into your land planning, design, land development and maintenance practices.

Instead of bellyaching about what others are going to make local municipalities do, lets take the lead in doing the right thing and pursue good houskeeping measures in our metropolitan area. We now have a much better understanding of the effects of urbanization on stormwater runoff and its effects on receiving waters. We also have the basic tools to mitigate some of these effects. We will not be able to eliminate the effects of urbanization on our environment, but we certainly can reduce and contain many of these effects through the use of BMPs and good housekeeping. The use of these, in combination with measures to stabilize our waterways should leave behind improved greenbelts with better wildlife and aquatic habitats and populations for our citizens to enjoy.

MAINTENANCE PROGRAM ACTIVITIES

by: Mark R. Hunter, P.E. Chief, Maintenance Program

STATUS OF MAINTENANCE REHABILITATION PROJECTS

Project Jurisdiction Cost   Status
ADAMS COUNTY        
Grange Hall Creek-east of Irma Northglenn design $20,000 delayed
detention pond repairs   const 150,000 0%
Niver Creek-Huron to Zuni Thornton design 25,343 100%
erosion repair   const. 279,920 0%
Westerly Creek-north of Montview Aurora design 48,743 90%
Replace pipe with channel   const. 175,000 0%
ARAPAHOE COUNTY        
Big Dry Creek-Nobles Rd.Trib Arapahoe Co. design $74,653 100%
east of University   const 220,000 0%
Greenwood Gulch-east of Holly Greenwood Vilage design 40,000 0%
erosion repair   const 250,000 0%
South Platte - Col.Valley Columbine Valley design by others 100%
Trickle channel   const 20,000 100%
West Harvard Gulch Englewood design 22,340 60%
pipe replacement   const 225,000 0%
W. Toll Gate Ck.-Delaney Farm Aurora design 30,000 0%
north of Alameda   const 275,000 0%
W. Toll Gate Creek Arapahoe Co. design by others 100%
Peakview pond repair   const 89,159 100%
BOULDER COUNTY        
Bear Canyon Creek Boulder design $30,000 100%
Drops,bank repair w/city   const 278,300 100%
Bear Canyon Creek Boulder design 30,000 postponed
Martin Pk drops,bank work   const 120,000 postponed
Bear Canyon Creek Boulder design 15,000 postponed
Mohawk Drive   const 80,000 postponed
Coal Creek Superior design by others 100%
at 2nd Avenue   const 15,000 0%
Gregory Canyon Ck Boulder design by others 100%
with Boulder and Capital   const 75,000 85%
DENVER COUNTY        
Cherry Creek Denver design $49,514 100%
Drop structure (Monaco)   const 214,311 100%
Cherry Ck - Babi Yar Denver design 34,865 95%
Drops, bank repair   const 135,000 delayed
Cherry Ck - Delgany,Market Denver design 26,850 100%
Bank repair and ramp   const 241,650 100%
Goldsmith Gulch Denver design 43,500 10%
Bible Park low flow channel   const 85,000 delayed
Goldsmith Gulch Denver design 35,000 0%
Cook Park low flow channel   const 150,000 0%
Goldsmith Gulch Denver design 65,341 100%
Rosamond Park   const 368,081 100%
Lakewood Gulch Denver design 78,432 90%
Channel repair   const 300,000 0%-phase 3
Montbello Drainage (w/city) Denver design by others 100%
Concrete channel repair   const 44,000 100%
South Platte River Denver design 34,271 95%
Westside trib.   const 95,000 0%
Weir Gulch Denver design by others 50%
Barnum Park detention   const 75,000 0%
DOUGLAS COUNTY        
East Dad Clark Gulch Douglas Co. design $22,826 70%
improve existing drop   const 175,000 0%
JEFFERSON COUNTY        
Airport Creek Westminster design $81,962 100%
Eaton and 112th   const 310,000 0%
Lena Gulch Lakewood design 46,747 100%
From 20th to Youngfield   const 279,976 98%
SJCD (So) Jefferson Co. design 34,830 95%
Carr to Estes   const 250,000 delayed

Program Direction

An increasing awareness of the recreational and ecological values of urban drainageways has encouraged interaction among engineers, landscape architects, planners, and neighborhood representatives. This approach requires the combination of diverse interests during the initial design phase of a project. This should result in drainageway projects that are functional, attractive, cost effective, and protective of the environment. Some of the larger maintenance projects have generated this level of attention. They are discussed in more detail below under rehabilitation maintenance.

In 1995 two events occurred that shaped a good share of the maintenance activities for the year. The long period of spring rains brought us welcome moisture but also caused erosion damage to trails and stream banks on several creeks in the District. Some specific projects that resulted from the spring rains are discussed below. The other 1995 event was the wet snowfall on September 20. It was reported that 80% of the trees in the Denver Area were damaged by the heavy snow. Local governments responded by picking up broken branches in the street right-of-way. The District picked up broken branches from many of the drainageways we maintain. Many local governments provided a dump site for us at no charge. Even so, we spent $116,000 throughout the District picking up broken tree limbs.

Routine Maintenance

Under the routine program $540,000 was spent in 1995 for mowing and debris pickups on approximately 205 different sections of drainageways within the District boundaries. This equates to a total of nearly 100 miles of drainageways in the Denver area that were given routine maintenance.

Some of the drainageways we maintain are quite urbanized with adjacent homes, streets, and improved parks. Other drainageways we maintain are more rural in character. On portions of some of these more rural drainageways we have taken the opportunity to reduce or eliminate our mowing activities. This has been done to encourage habitat and leave a more natural character in the corridor.

Restoration Maintenance

In 1995 the restoration program completed $1.14 million of work. This was the result of 84 individual projects that addressed isolated drainage problems on major drainageways.

Between the foothills and Denver Clear Creek flows through the City of Wheat Ridge. In two separate locations the spring rains and steady high flows on the creek eroded the bank so much that the adjacent trail was undermined. Addressing these problems promptly was important in order to prevent further erosion and damage to public facilities. The City of Wheat Ridge participated in funding these repairs. This allowed us both to get more work done within our budget constraints. The solution was to rebuild the banks and armor them with riprap.

The high flows this spring also caused erosion on about 300 feet of Cherry Creek immediately upstream of its confluence with the South Platte River. Our solution was to install a low wall of boulders to stop the erosion. The boulder wall is consistent with improvements that have been made on several other parts of Cherry Creek. We were unable to get to the project immediately because relatively high flows on the creek continued well into the summer.

Two creeks in Boulder County were damaged by the spring rains. Five separate locations of the concrete access trail on Boulder Creek in Boulder were either undermined or buried by sediment. Repair of these sites involved using riprap and boulders to reinforce the creek bank. Severe damage occurred to the access trail along Coal Creek through the unincorporated portions of Boulder County near Louisville and Lafayette. This trail was originally constructed of compacted "crusher fines" and followed an alignment that, in some sections, was within a few feet of the creek bank. At those locations where the high runoff inundated the trail the water swept away all the aggregate. It was illuminating to recognize that the trail was the only item damaged as even the vegetation adjacent to the trail withstood the erosion.

In past issues of Flood Hazard News we reported that some of the concrete-lined channels in the Montbello area of northeast Denver had been damaged. Inadequate reinforcement, thin concrete sections, and lack of weep drains were blamed for the failures. This type of failure continued this year with the bottom and side panels being torn out of a forty foot long section. We installed a temporary repair of riprap and will soon construct a concrete channel for the full length of the 610 foot long block.

In an urban area a drainageway full of vegetation can present a dilemma to local jurisdictions. If the creek was originally confined by development there may be so little surplus flood-carrying capacity in the channel that there is no room for additional tree and shrub growth. As a drainage basin is developed base flows in the creek typically increase, resulting in expanding vegetation growth. While the vegetation is generally welcomed by all of us the additional vegetative growth directly reduces the flood carrying capacity of the creek. Removal of selected vegetation can become necessary in order to retain the flood capacity of the creek.

Since 1981 we have occasionally carried out tree-thinning operations on Cherry Creek in Denver from University Boulevard to Iliff Avenue. In 1995 we again thinned the trees in this reach of Cherry Creek. As in the past we conducted engineering studies to assess the resistance to flow caused by the tree growth. We held meetings with the neighborhoods along the creek and also consulted with wildlife specialists and the Denver Forester's office. The result was a limited tree thinning operation during the late winter which is a period of relative inactivity for animals and trees. We removed only that percentage of trees that was necessary to return the necessary flood-carrying capacity to Cherry Creek. Managing tree growth is a never ending activity so we anticipate doing this kind of work on Cherry Creek on a regular basis.

Rehabilitation Maintenance

Twenty-eight projects were at various stages of design or construction during 1995. Those projects are listed in the accompanying table titled "STATUS OF MAINTENANCE REHABILITATION PROJECTS". By the end of 1995 the District will have spent about $827,000 on rehabilitative design and construction for the year. A few of the unique projects are discussed below.

As the activity at Stapleton Airport has diminished our project on Westerly Creek immediately south of the airport has changed. Our recommended solution to the collapsing 60" pipe is still to replace the pipe with an open channel. But, with closure of the airport, land use considerations are changing. This has delayed the acquisition of the necessary easements.

The design has just been completed for the rehabilitation of Airport Creek at 112th Avenue and Harlan Street in Westminster. A landscape architect is the prime consultant for this project to correct the localized aggradation and degradation. The wide drainageway corridor permitted the consultant to take advantage of the gently graded open space to design the drainage repairs and incorporate some aesthetic features.

The heavy spring runoff severely damaged a drop structure and about 100 feet of gabion bank protection on Lena Gulch. The site is downstream from the Consolidated Mutual water treatment plant at 27th Avenue in Lakewood. Repairing the damage is a top priority for the local governments in the area. Design is well underway with both the Maintenance Program and the Design and Construction Program of the District participating in the project. In order for the Maintenance Program to participate funds had to be re-prioritized from a bank stabilization project proposed for Lena Gulch just downstream of the damaged drop structure. The bank stabilization has been re-scheduled to 1996.

Before After

A portion of the Clear Creek trail before and after repairs.

cherrycf.jpg (56164 bytes)

Low flow channel repairs on Cherry Creek near the confluence.

The Design and Construction Program is participating in construction of improvements on Goldsmith Gulch at Yale Avenue and also at Dartmouth Avenue. Between those two streets is Bible Park. Within Bible Park the low flow channel for Goldsmith Gulch has eroded into a vertical-sided channel ranging from three to ten feet deep. The Maintenance Program will rehabilitate the eroded channel. In addition to repair to the channel the opportunity exists for park-related aesthetic and habitat improvements. Denver Parks Department, neighborhood representatives, design consultants, and Maintenance Program staff have begun a series of meetings and working sessions that will produce the desired concept for improvements to the Goldsmith Gulch channel and adjacent park land.

Another section of Cherry Creek has been improved with boulder edging of the low flow channel. The District funded the boulder edging work as part of the Greenway Foundation's project to build a series of temporary boating pools in the creek. The project is located between Delgany Street and Market Street and included a new access ramp into Cherry Creek.

Four years ago the Maintenance Program repaired a portion of Lakewood Gulch on the east side of Federal Boulevard in Denver. It consisted of short vertical structural walls to control the erosion. The section to be rehabilitated now is to the west of Federal Boulevard. The design of this section has been a process of evaluating the severity of the damage and assessing the appropriate repairs. The process has resulted in a design that is less structural than shown in the original concept and a design that is far less structural than the project east of Federal Boulevard.

MOUSE MAY IMPACT PROJECTS

by: Mary L. Powell, Environmental Specialist MDG & Associates, Inc.

The Preble's meadow jumping mouse (Zapus hudsonius preblei) is a small, long-tailed mouse with hind legs much longer than its forelegs. It occurs mostly in low undergrowth with grasses or other nonwoody plants, or both. It can also be found in open, wet meadows and riparian corridors near forests or where tall shrubs and low trees provide adequate cover.

The U. S. Fish and Wildlife Service (USFWS) has initiated the process required to list the Preble's meadow jumping mouse as threatened or endangered under the Endangered Species Act (ESA). If the species is listed as threatened or endangered all federal agencies must ensure that actions which they fund, approve, or carry out do not "jeopardize" the species or adversely affect its designated critical habitat. Additionally, all persons, public or private, must comply with the prohibitions of the ESA, including the prohibition of "take" of listed fish and wildlife species.

The Urban Drainage and Flood Control District must apply for 404 Permits from the U. S. Army Corps of Engineers for most of its projects. If the mouse is listed as threatened or endangered, the District will be required by the Corps to determine the presence or absence of the mouse before beginning work on those projects.

MDG & Associates (one of the District's revegetation and ecological consultants) has compiled the following list of questions and answers regarding the ESA listing process and possible consequences.

What are the steps required to actually list the mouse? There are four steps:

1. Petition for listing - On August 16, 1994, the USFWS received a petition from the Biodiversity Legal Foundation to list the mouse as threatened or endangered. Such a petition must support its claim with credible data and research. The USFWS has up to 90 days to accept the petition.

2. 12-month finding - The USFWS has one year to review the accepted petition for listing of the mouse. After this review a 12-month finding is published. The 12 month finding will provide a summary of research on the known populations of the mouse, on mouse habitat, and on historic and current threats to the mouse and its habitat.

3. Public comment period - Following the publication of the 12 month finding, there will be a 60 day period for public comment on the listing of the mouse. If requested, a public hearing must be held within 45 days.

4. Final Determination - The USFWS has one year from the publication of the 12 month finding to determine the final status of the mouse. The USFWS will recommend listing the mouse if it finds that mouse populations are in danger of precipitous declines and that no local, state, or federal actions are being taken to conserve the mouse.

Where are they in the listing process? Currently, the USFWS is planning to publish the 12-month finding prior to the end of 1995.

How likely is it that the mouse will be listed? And when? Very likely. Late 1996 or early 1997.

How much of the District's jurisdiction is possible mouse habitat? Based on current information, most of the areas under District jurisdiction will not prove to be appropriate mouse habitat. When applicable, a letter from a certified mouse habitat surveyor excluding the site from survey requirements will probably satisfy ESA requirements, including 404 permit requirements.

Is there a minimum size of habitat required to support the mouse? It depends on the quality of the habitat. Typically, the mouse has a home range of between 1/2 and 1 acre.

Will the mouse recolonize disturbed areas? It depends on the habitat present before the disturbance, on the habitat that exists following the disturbance, and the presence of a source of recolonizing mice. If the site was previously mouse habitat and disturbance is low to moderate, recolonization is possible if mice can move back into the site. If the site has been greatly modified, such as complete regrading of a site, recolonization is very unlikely.

Do mowing activities affect the mouse, and are mowing activities covered by the Endangered Species Act? If the area has not been mowed in the past and is mouse habitat, it is likely that the mouse would be affected. If the mowing has been on-going for some time, that activity will not be a problem (no mice). Mowing is covered under the Act if it modifies critical habitat to the exclusion of mouse use.

Are sedimentation removal projects going to require a survey? What about disturbance from access to the site? Sedimentation removal projects will probably not require a survey. Unless the disturbance from construction access is permanent, that is probably not a problem either.

If the mouse is listed, will on-going projects be affected if they already have 404 permits? Yes. Projects will still require a finding of "No Jeopardy" if they are in potential mouse habitat.

Are there any habitats exempt from the survey? Yes, riprap, heavily overgrazed areas, historically mowed areas, landscaped and maintained lawns, monocultures of cattails, and areas continually inundated by standing water are exempt. Additionally, the USFWS has not included the City and County of Denver in its survey requirements although some areas in Denver have been identified as medium to high priority as potential habitat (i.e. Bear Creek).

What does a survey for the mouse involve? The surveys for the mouse must be done when the mouse is most active - nights from May 31 to September 15. A survey involves setting traps over the course of four nights. Each survey site must have a total of at least 400 trap-nights (e.g. 100 traps each night for four nights). A team of at least two qualified surveyors must check the traps several times during each night. For each small mammal trapped, information must be collected on species, length, weight, sex, and age. If a Preble's mouse is trapped it must be photographed and hairs must be collected for genetic analysis. The survey report includes detailed descriptions of the site including soils, hydrology, vegetation, and geomorphology.

What are possible consequences to the District? The results of listing the mouse are uncertain. It is very likely that the US Army Corps of Engineers will require addressing the mouse in its permitting process. If the mouse is found at a project site, the USFWS must be consulted to determine reasonable and prudent alternatives that may involve any of the following: 1) move the project location 2) change the timing of the project 3) reduce the project size 4) modify the project scope 5) provide additional protection and /or habitat for a listed species.

Grouted Sloping Boulder Drop Structures - A Success Story

by Bill DeGroot, P.E. Chief, Floodplain Management Program

In 1985, the District retained the firm of McLaughlin Water Engineers, Ltd. to assist in a major revision of the "Structures" chapter of Volume 2 of the Urban Storm Drainage Criteria Manual. Our focus was on improving the variety and design guideance for drop structures used in the commonly encountered urban drainage situations. The effort was completed under the direction of Bill Taggart.

A thorough literature review was conducted; as was an evaluation of many drop structures which had already been constructed in the Denver area, and which could give some real life experience to the study effort. The information garnered in these investigations was utilized to assist in the completion of a significant amount of computer modeling and other design efforts to arrive at four drop structure designs which were included in the revised "Structures" chapter.

In the years since distribution of the revised chapter, one of the four drop structures, the grouted sloping boulder (GSB) drop structure, has become the overwhelming favorite of both local governments and private developers. Its versatility and aesthetic features have made it the favorite. This photo essay demonstrates several of the different applications for this design.


The GSB can be used for almost any practical drop height, in this case a 20 foot high drop on SJCD (South) in Littleton.

The GSB has the versatility to "hook on" to an existing structure to extend its vertical distance, here on Cherry Creek.

The GSB can be used for low flow checks, as in this
application on Cherry Creek.

In a drainageway with a base flow the GSB can be aesthetically pleasing as is this one near Cherry Creek shopping center.

 

Looking upstream     Looking downstream
The GSB can be modified for special applications, in this case the Creekfront project on Cherry Creek in downtown Denver.
These two pictures are looking upstream and looking downstream.
    Replacement drop structure
The Maintenance Program uses t